The expansion of the infrastructure of water supply and wastewater treatment and the construction of the sewage treatment plant in Naujuju Valkininku village Varena district.
While the implementation of   this project in Naujuju Valkininku village Varena district, water supply and wastewater networks were expanded. During the construction period more than 4,2 km of different water supply, wastewater sewer, pressurized sewage networks were installed, 3 domestic wastewater pumping stations  were built.
The construction work was financed by The European Union Cohesion Fund and the state budget of the Republic of Lithuania.

 

The construction of intermodal terminal in Kaunas‘ Public Logistics Centre. The installment of the outside water supply and wastewater networks

In this newly built intermodal terminal in Kaunas water supply, domestic wastewater and rainwater networks were installed. During the construction period more than 4,9 km of different diameter water supply, domestic wastewater and rainwater networks were equipped.   

 

The expansion of water supply and wastewater networks in Kaunas, Vilijampole
During the construction period more than 40, 8 km of different diameter water supply, wastewater sewer, pressurized sewage networks were installed, 3 domestic wastewater pumping stations  were built. 
 
 
 

The new construction of water supply and wastewater networks in Pavilnys. Design and building.
During the process of construction more than 18,3 km of different diameter of water supply, wastewater sewer, pressurized sewage networks were installed, 2 domestic wastewater pumping stations  and a third lifting water pumping  were built.
 
 

The construction of the intersection of IXB transport corridor (Žirnių st.) and Vilnius international airport. Rainwater networks

During 4 months of the project implementation more than 3,2 km of different diameter (till DN 1600) wastewater sewer networks were installed 7 m deep.  

The general contractor of the object is AB „Kauno tiltai“.

 

The expansion of water supply and wastewater networks in Varena in the individual housing estate in Marcinkoniu st.
After the implementation of this project in Varena water supply and wastewater networks were expanded. During the process of construction more than 4,4 km of different diameter water supply, wastewater sewer, pressurized sewage networks were installed, a domestic wastewater pumping station  was built.
 

The expansion of water supply and wastewater networks in Kazlu Ruda . III stage
After the implementation of this project in Kazlu Ruda  water supply and wastewater networks were   expanded. During the process of construction more than 14,1 km of different diameter water supply, wastewater sewer, pressurized sewage networks were installed, 4 domestic wastewater pumping stations  were built.
 
 

The construction of a shopping center in Žirnių st., Vilnius. The installment of outside water supply and wastewater networks
During the implementation of this project more than 8 km of different diameter water supply,  self- flowing domestic wastewater and rainwater networks, filtration rainwater containers were installed. The work was a component of the construction of IKEA shopping center in Vilnius.   
 

The construction of water supply and wastewater networks in Pavilnys settlement
In Pavilnys settlement water supply and wastewater networks were expanded. During the process of construction more than 14, 5 km of different diameter  water supply, wastewater sewer, pressurized sewage networks were installed, 4 domestic wastewater pumping stations  were built.
 

The expansion of water supply and wastewater treatment facilities in Ringaudai, Kaunas district
While the  implementation of    this project water supply and wastewater  networks were expanded. During the process of construction more than 8, 5 km of different diameter  water supply, self- flowing and  pressurized sewage networks were installed. 
 

The expansion of water supply and sewer system in Alytus. V part.
During the process of construction more than 21km of different diameter  water supply, self-flowing and pressurized sewage networks were installed, 3 domestic wastewater pumping stations  were built.
 

 

The expansion of water supply and domestic sewer system in Miklusenai

During the process of construction more than 14km of different diameter  water supply, self-flowing and pressurized sewage networks were installed, 4 domestic wastewater pumping stations  were built.

 

The construction and establishment of the industrial park in Alytus
While the implementation of  this project 857 m Ø 315- 800 of domestic wastewater and rainwater networks, 294 m Ø315 of water supply networks were installed. The work was performed under the complicated circumstances at a very different geological soil incision and high groundwater. The networks were installed 7 m deep.
 

Extension of drinking water and sewerage water networks in Lentvarys. II construction stage
In total 9000 m of drinking water networks DN100-300; 200 m of gravity sewer network DN300; three premanufactured waste water pumping stations DN1600 have been installed. Works have been executed within the town precincts, using formwork panels.
 
 
 

Design and reconstruction works of drinking water pipe in Draugystes street
Mostly the construction works have been carried out in the open trench, only under the railway, heating supply line and Pramones street pipes have been installed by trenchless method. Draugystes street locates at the industrial city area with many plants, administration buildings and trading centers, thus all new service connections were performed in the most comfortable way for existing consumers.
 
 

Extension of drinking water and sewerage networks in Kalvarija
Kalvarija town is situated on the Šešupė river bank, therefore in many places pipes were laid lower than the ground water level. However this issue did not make any troubles for the specialists. Ground water level has been lowered using the needle filters equipment. 
 

Reconstruction of LA military air force aviation base main take off and landing runway . Storm water networks
This project has been financed from NATO budgeе. In total 713 m of PVC storm water networks DN400, 315 mm has been constructed. Installation depth form 2 to 4,5 m. Due to high ground water it has been needed to lower ground water horizon level during construction works.

Lifting sewage network at Kaunas city entertainment and sport house in Nemunas island with infrastructure part B stage II

During project 155 metres of Ø600- Ø800 mm pressure sewage line from ductile cast-iron pipes was rebuilt where installation deepness was from 5 metres.